Typical Special Requirements
1. The cooling tower should be located on the roof of the power building. Sometimes decorative walls can also provide a challenge. For this particular site, there are decorative walls that are 7 meters high. The lower section is 5.5 meters tall, and has louvers, providing fresh air to the north and south sides.
2. There’s a fresh air inlet for generators in the center of the roof. The tunnel is 3.5 meters tall, including a 2.5 meters tall louver. There are six generator air outlets underneath the roof.
3. For emergency situations in which all generators will be put into operation, the total inlet air volume necessary to start the generator is 1,280,000 m3/h. |